Overview
Horner & Shifrin performed the repair and restoration of an open channel upstream and downstream of a new road crossing. The area of stabilization had a total length of approximately 320’, of which, 240’ was upstream of the new crossing and 80’ downstream of the structure. The project utilized a combination of fixes that included Curlex bloc logs and live stakes for toe protection, Curlex III erosion control blankets with a native seed mix for bank protection, and light limestone revetment grade controls to stabilize the stream bed.